Rm18-1806 (phase 3) repair railroad culvert rm 36.09: firm fixed-price (ffp) for all labor, materials, equipment and associated costs related to rm18-1806 (phase 3) repair railroad culverts rm 36.09 bremerton, wa.. Contracting activity: NAVFACSYSCOM NORTHWEST. Estimated completion: 2027-02-11.
$12.1M total obligated / Competition not stated / 2027-02-11 completion / N44255 NAVFACSYSCOM NORTHWEST
1. Contract Summary & Primary Sources
| Contract Number (PIID) | N44255-25-F-0216 (unhyphenated: N4425525F0216) / Parent Vehicle: N44255-23-D-1600 |
|---|---|
| Prime Contractor (Awardee) |
Port Madison Construction Corporation
(Washington)
FY2024-FY2026 Federal Defense Portfolio: $83.0M obligated across 126 contracts
|
| Total Obligated (all actions) | $12,063,012 ($12.1M) |
| USAspending / FPDS Obligation History | Total obligated: $12,063,012 (signed 2025-08-20, latest FPDS action 2025-08-20) / 15 Issued Delivery/Task Order(s) totaling $38,555,551 |
| Awarding Branch / Agency | Department of the Navy |
| Contracting Command & DoDAAC | N44255: NAVFACSYSCOM NORTHWEST |
| Competition & Contract Structure | Competition not stated / Delivery Order (delivery order) / Firm-Fixed-Price (FFP) |
| Product / Service & Industry Codes | PSC Z1LB (Maintenance Of Highways/Roads/Streets/Bridges/Railways) / NAICS 236220 (Commercial And Institutional Building Construction) |
| Work Locations & Funding | Primary Place of Performance: Washington |
| Estimated Completion Date | 2027-02-11 |
| Verified Primary Sources |
2. Verbatim Announcement & Scope Breakdown
Rm18-1806 (phase 3) repair railroad culvert rm 36.09: firm fixed-price (ffp) for all labor, materials, equipment and associated costs related to rm18-1806 (phase 3) repair railroad culverts rm 36.09 bremerton, wa.
3. Subcontractor, Supply Chain & Capture Intelligence
Subcontracting & Material Supply Window
- Prime Awardee: Port Madison Construction Corporation
- Delivery Runway: Active through 2027-02-11
- Requirement Scope: Rm18-1806 (phase 3) repair railroad culvert rm 36.09: firm fixed-price (ffp) for all labor, materials, equipment and associated costs related to rm18-1806 (phase 3) repair railroad culverts rm 36.09 bremerton, wa.
- Federal Supply Class: PSC Z1LB (Maintenance Of Highways/Roads/Streets/Bridges/Railways)
- BD Action: Reference Prime Contract N44255-25-F-0216 when contacting Port Madison Construction Corporation Supply Chain / Small Business Liaison Officer.
Buying Command & Recompete Posture
- Buying Command: N44255 (NAVFACSYSCOM NORTHWEST)
- Acquisition Method: Competition not stated
- FOIA Jurisdiction: Department of the Navy FOIA (route via DON portal) (Official Portal)
- Capture Action: Request Section B CLIN ceiling structure and Section C Statement of Work below to benchmark deliverable requirements.
Issued Task & Delivery Orders under N44255-25-F-0216 (15 shown, $38.6M obligated)
| Order PIID | Obligated | Awardee | Start / Latest Action | End Date | Order Scope |
|---|---|---|---|---|---|
| N4425524F4251 | $5.2M | Port Madison Construction Corporation | 2024-07-25 / 2025-05-02 | 2025-11-24 | Replace various pump-house systems, building 7427, naval base kitsap. |
| N4425525F0075 | $4.7M | Port Madison Construction Corporation | 2025-05-22 / 2025-05-22 | 2026-05-26 | Contractor to remove and repave delta pier, south trestle, north trestle and delta drydock surfaces. work includes minor repairs to sub-base layers and the restriping of all pavement markings. regrade escolar road intersection. |
| N4425526F0167 | $3.9M | Port Madison Construction Corporation | 2026-05-29 / 2026-05-29 | 2027-12-06 | Remove and replace otto fuel tanks a and b and reconfigure tank p as per design specifications. |
| N4425525F0178 | $2.9M | Port Madison Construction Corporation | 2025-07-23 / 2025-07-23 | 2026-07-18 | Design-bid-build - firm fixed-price (ffp) for all labor, materials, equipment and associated costs related to the roof replacement at barracks b373 through b379 (seven roofs) per the work package and not including work identified in any ... |
| N4425524F4247 | $2.8M | Port Madison Construction Corporation | 2024-06-18 / 2026-05-04 | 2025-10-17 | X001 msr #22272591_1770580 -- 22272591 modify thermal relief syst |
| N4425525F0020 | $2.7M | Port Madison Construction Corporation | 2025-04-23 / 2025-04-23 | 2026-10-26 | Special project rm027-04 for repair of pumpwell 2 main dewatering pumps and motors split this into two circuits, 480- 9-10 and 412-10-5b to serve new equipment at elec. substation 10. portion of circuit 448-fg-9 is degraded and beyond ... |
| N4425525F4048 | $2.3M | Port Madison Construction Corporation | 2025-01-24 / 2025-09-19 | 2026-08-27 | Navfac northwest 8(a) macc modernize elevator #1, b107 |
| N4425525F0261 | $2.3M | Port Madison Construction Corporation | 2025-09-19 / 2025-11-17 | 2026-09-12 | Drainage improvement tank containment b2910, t1 - design-bid-build construction task order |
| N4425524F4337 | $2.1M | Port Madison Construction Corporation | 2024-08-20 / 2026-05-21 | 2026-08-25 | X003 msr #22272317_1777243 -- (ih-db_22272317) install gravity se |
| N4425524F4338 | $2.0M | Port Madison Construction Corporation | 2024-08-09 / 2024-08-09 | 2025-10-17 | Replace deteriorated watermain supply line, kodiak-pw |
| N4425525F0214 | $1.8M | Port Madison Construction Corporation | 2025-09-18 / 2026-04-29 | 2026-08-14 | Reconfigure and renovate rooms and trailers b7450 trf |
| N4425525F4107 | $1.8M | Port Madison Construction Corporation | 2025-03-14 / 2025-03-14 | 2026-03-12 | Replace stairway handrails, 705, psns |
| N4425525F0036 | $1.7M | Port Madison Construction Corporation | 2025-05-02 / 2025-05-02 | 2026-10-26 | This construction project will a design-build contract to include design, labor, materials, and equipment to replace the existing oil-water separator (ows) 6a located at manchester fuel depot (mfd). |
| N4425524F4176 | $1.3M | Port Madison Construction Corporation | 2024-05-06 / 2025-05-21 | 2025-09-30 | Fy24 airfield maintenance |
| N4425524F4356 | $1.2M | Port Madison Construction Corporation | 2024-08-20 / 2024-08-20 | 2024-12-19 | Repair sink holes at naval base kitsap. |
Recent Contract Actions from Buying Office N44255 (NAVFACSYSCOM NORTHWEST)
| Date | Contract (PIID) | Prime Contractor | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2026-09-30 | N44255-26-D-1811 | Alberici Constructors Inc., Caddell Nova JV. Montgomery, CDM Constructors Inc. and Clark Orion JV | $9.0B | 2034-09 | New design, construction, supervision, equipment, material and labor for renovation, repair, and new construction of facility construction p... |
| 2026-09-30 | N44255-26-D-0003 | Stantec-TranSystems JV | $249.0M | - | Multi-disciplinary architect and engineering services |
| 2026-08-07 | N44255-21-D-5003 | Contrack Watts Inc | $326.0M | - | Contrack Watts and 7 others share $326.0M modification for bilateral modifications to their respective waterfront multiple award constructio... |
| 2026-08-06 | N44255-20-D-0002 | Rogers, Lovelock & Fritz | $127.0M | - | Rogers, Lovelock & Fritz wins $127.0M contract for multi-discipline projects at various activities in the Naval Facilities Engineering Syste... |
| 2026-07-30 | N44255-26-D-1501 | Manson Construction Co | $700.0M | - | Manson Construction and 8 others share $700.0M contract for new construction, renovation, alteration, demolition. Naval Facilities Engineeri... |
| 2026-07-17 | N44255-26-D-0008 | Trevet-NOREAS JV | $45.0M | - | Trevet-NOREAS JV wins $45.0M contract for architect engineer services for environmental restoration services. NAVFAC Northwest $10K obligate... |
| 2026-05-14 | N44255-26-D-0001 | WSP Solutions | $249.0M | - | WSP Solutions wins $249.0M contract for architect-engineer services. Naval Facilities Engineering Systems Command signed May 13, 2026. |
| 2026-01-29 | N44255-23-D-1600 | Port Madison Construction Corporation | $110.0M | - | Port Madison Construction and 9 others share $110.0M modification for new construction, renovation, alteration, demolition, and repair of fa... |
Other Recent Department of War Awards to Port Madison Construction Corporation
| Date | Contract (PIID) | Branch | Amount | Completion | Scope Summary |
|---|---|---|---|---|---|
| 2026-01-29 | N44255-23-D-1600 | Navy | $110.0M | - | Port Madison Construction and 9 others share $110.0M modification for new construction, renovation, alteration, demolition, and repair of fa... |
| 2025-09-24 | N44255-25-D-6000 | Navy | $99.0M | - | Port Madison Construction wins $99.0M contract for construction projects to include repairs, rehabilitations. Naval Facilities Engineering S... |
4. Underlying Contract Files (Section B Pricing & Section C Statement of Work)
Pre-Filled FOIA Request Letter for N44255-25-F-0216
Routed to Department of the Navy FOIA (route via DON portal) / Official Agency FOIA Portal ↗
Export Contract Dossier & Related Awards
Download this contract record, sibling orders, and buying office awards in CSV, JSON, or Markdown Brief, or query via the AwardTape API & MCP server.
Building an AI agent? Get this award as JSON: GET /api/agent/v1/awards?q=N4425525F0216. Schema, sample and price or start with free sample calls.