| FA441725F0278 | $1.7M | delivery order | Department of the Air Force | New construction | Work to be performed under this task order will be in accordance with the statement of work, accepted proposal and drawings attached in section j | Mar 5, 2026 |
| FA248826FB008 | $715K | delivery order | Department of the Air Force | Real property maintenance and repair | Construct concrete targets do #12 | May 20, 2026 |
| FA248826FB006 | $536K | delivery order | Department of the Air Force | Real property maintenance and repair | Construction concrete targets do #11 | Apr 13, 2026 |
| FA248825FB013 | $495K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023 - drawings 23-ta-c74-01 r1 dated 13 march 2023 | Sep 2, 2025 |
| FA441725F0206 | $470K | delivery order | Department of the Air Force | Equipment maintenance, other | Repair hot water supply and return lines on the building 1 boiler | Nov 18, 2025 |
| FA248825FB008 | $398K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023- drawings 23-ta-c74-01 r1 dated 13 march 2023 | Apr 21, 2025 |
| FA248826FB003 | $382K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023 - drawings 23-ta-c74-01 r1 dated 13 march 2023 | Mar 26, 2026 |
| FA441724F0123 | $349K | delivery order | Department of the Air Force | Real property maintenance and repair | The work to be performed in accordance with sow to include, but not limited to: 1. crack repairs will be sealed with backer rod and cold applied joint seal.2. spalls to be repaired within limits of the east ramp and runway as shown on the ... | Jun 13, 2024 |
| FA441726F0027 | $340K | delivery order | Department of the Air Force | Real property maintenance and repair | Repair spalls and cracks in accordance with the attachments listed in section j | Mar 11, 2026 |
| FA441724F0153 | $305K | delivery order | Department of the Air Force | New construction | The work is but not limited to repair, replacement, and minor construction of base pavements, water distribution systems, wastewater distribution systems, and other related work at hurlburt field, fl. | Jul 5, 2024 |
| FA441725F0222 | $301K | delivery order | Department of the Air Force | New construction | This is a civil works idiq contract for work consisting of, but not limited to, repair, replacement, and minor construction of base pavements, water distribution systems, and other related work at hurlburt field, fl. | Apr 21, 2026 |
| FA248825FB007 | $277K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023- drawings 23-ta-c74-01 r1 dated 13 march 2023 | Feb 21, 2025 |
| FA441724F0127 | $271K | delivery order | Department of the Air Force | New construction | The contractor shall furnish all labor, materials, tools, supervision and equipment and perform all operations necessary to repair vcp sewer lines within basin 2. the project is located on hurlburt field, fl. | Nov 4, 2024 |
| FA248824FB001 | $267K | delivery order | Department of the Air Force | New construction | Construct concrete targets do 03 | May 29, 2024 |
| FA248824FB003 | $225K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023- drawings 23-ta-c74-01 r1 dated 13 march 2023 | Jun 5, 2024 |
| FA441725F0119 | $196K | delivery order | Department of the Air Force | New construction | Repair seven stormwater systems around hurlburt field, florida. | May 15, 2025 |
| FA441725F0017 | $195K | delivery order | Department of the Air Force | New construction | Repaint runway edge lines | Jan 10, 2025 |
| FA441724F0039 | $181K | delivery order | Department of the Air Force | Architect-engineering services | Repaint edge lines and red lines | Apr 2, 2024 |
| FA441726F0015 | $165K | delivery order | Department of the Air Force | New construction | Cp1145982 runway rubber removal 18/36 | Feb 5, 2026 |
| FA441725F0199 | $161K | delivery order | Department of the Air Force | New construction | Cp1144587 eod armag work to be performed under this task order will be in accordance with the statement of work, accepted proposal and drawings attached in section j. | Dec 19, 2025 |
| FA441725F0020 | $159K | delivery order | Department of the Air Force | New construction | This is a task order off of the civil works idiq contract for annual rubber removal requirement | Mar 21, 2025 |
| FA441725F0272 | $141K | delivery order | Department of the Air Force | Real property maintenance and repair | Contractor shall furnish all plant, labor, equipment, materials, facilities, and transportation necessary to repair sewer lines, iaw the drawings and specifications. | Jun 2, 2026 |
| FA441723F0124 | $120K | delivery order | Department of the Air Force | Real property maintenance and repair | Maintain perimeter fence | Jul 19, 2024 |
| FA441723F0169 | $113K | delivery order | Department of the Air Force | Real property maintenance and repair | Correct flooding hamby pl - | Dec 23, 2024 |
| FA441724F0359 | $109K | delivery order | Department of the Air Force | Plumbing, heating and waste disposal | The contractor shall furnish all labor, materials, tools, supervision, and equipment and perform all operations necessary to accomplish all work complete to install communications infrastructure to building 91360, within hurlburt field, fl. | Feb 4, 2025 |
| FA441725F0262 | $107K | delivery order | Department of the Air Force | New construction | This is a civil works idiq contract for work consisting of, but not limited to, repair, replacement, and minor construction of base pavements, water distribution systems, and other related work at hurlburt field, fl. | May 4, 2026 |
| FA441724F0020 | $106K | delivery order | Department of the Air Force | Real property maintenance and repair | Remove rubber on runway 18/36 fy 24 | Jan 11, 2024 |
| FA441726F0021 | $86K | delivery order | Department of the Air Force | Real property maintenance and repair | The contractor shall remark/repaint and match all exiting striping as indicated in the work description within the sow and as shown on the included airfield site plan. | Apr 10, 2026 |
| FA248825FB004 | $74K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023- drawings 23-ta-c74-01 r1 dated 13 march 2023 | Dec 18, 2024 |
| FA441723F0320 | $72K | delivery order | Department of the Air Force | Plumbing, heating and waste disposal | Repair sewerage lift station 90027 | Feb 9, 2026 |
| FA441725F0211 | $58K | delivery order | Department of the Air Force | Real property maintenance and repair | The contractor shall furnish all labor, materials, tools, supervision and equipment and perform all operations necessary to repair by replacement the automatic access gate to the flightline. | Dec 29, 2025 |
| FA441724F0320 | $42K | delivery order | Department of the Air Force | Construction materials | The work consists of, but not limited to, repair, replacement, and minor construction of base pavements, water distribution systems, wastewater distribution systems, and other related work at hurlburt field, fl. | Sep 10, 2024 |
| FA441725F0246 | $35K | delivery order | Department of the Air Force | New construction | This is a civil works idiq contract for work consisting of, but not limited to, repair, replacement, and minor construction of base pavements, water distribution systems, and other related work at hurlburt field, fl. | Sep 4, 2025 |
| FA441725F0116 | $28K | delivery order | Department of the Air Force | New construction | Replace two concrete slabs on runway 18/36 | Jul 9, 2025 |
| FA441725F0106 | $26K | delivery order | Department of the Air Force | New construction | Duke field runway friction test | Apr 30, 2025 |
| FA441726F0033 | $24K | delivery order | Department of the Air Force | Real property maintenance and repair | Work performed under this task order will be in accordance with the statement of work (sow) and the attachments in section j. | Mar 18, 2026 |
| FA441723F0132 | $24K | delivery order | Department of the Air Force | Real property maintenance and repair | The contractor shall furnish all labor, materials, tools, supervision, and equipment and perform all operations necessary to accomplish all work as needed to repair spalls/cracks in apron, runways and taxiways plus storm drains and slabs | Sep 5, 2024 |
| FA441724F0299 | $12K | delivery order | Department of the Air Force | New construction | This is a civil works idiq contract for work consisting of, but not limited to, repair, replacement, and minor construction of base pavements, water distribution systems, and other related work at hurlburt field, fl. | Sep 6, 2024 |
| FA441723F0110 | $11K | delivery order | Department of the Air Force | New construction | Renovate airpark for public access | Jul 23, 2024 |
| FA282324F0065 | $10K | delivery order | Department of the Air Force | New construction | Construct concrete targets do 02 | May 14, 2024 |
| FA441723F0023 | $8K | delivery order | Department of the Air Force | New construction | Capital project 1132254 install communications conduit for fiber redundancy, 1 socs | Dec 15, 2023 |
| FA441723F0188 | $7K | delivery order | Department of the Air Force | Real property maintenance and repair | Correct parking lot flooding | Mar 26, 2024 |
| FA248825FB001 | $6K | delivery order | Department of the Air Force | New construction | Construct concrete targets requirements contract iaw: - specifications c-ve-23-01 dated 13 march 2023- drawings 23-ta-c74-01 r1 dated 13 march 2023 | Nov 5, 2024 |
| FA441724F0013 | $3K | delivery order | Department of the Air Force | New construction | Add handicapped parking bldg 1 | Nov 20, 2023 |
| FA282324F0051 | $1K | delivery order | Department of the Air Force | New construction | Construct concrete targets idiq / task order 0001 / kick off meeting | May 13, 2024 |
| FA282323F0192 | $0 | delivery order | Department of the Air Force | New construction | Construct concrete target delivery order 17 | Feb 22, 2024 |
| FA282324D0002 | $0 | IDIQ contract | Department of the Air Force | Real property maintenance and repair | Construct concrete targets requirements contract | Dec 1, 2025 |
| FA441723F0167 | $0 | delivery order | Department of the Air Force | Real property maintenance and repair | Award for repair leilmanis ave | Mar 4, 2024 |
| FA441723F0363 | $0 | delivery order | Department of the Air Force | Real property maintenance and repair | Repair stormwater drainage pipe, south west regional pond | Apr 9, 2024 |
| FA441724D0004 | $0 | IDIQ contract | Department of the Air Force | New construction | This is a civil works idiq contract for work consisting of, but not limited to, repair, replacement, and minor construction of base pavements, water distribution systems, and other related work at hurlburt field, fl. | Feb 5, 2026 |