Tracked vehiclesAnduril Enterprise 0.87% fill $173.4M / $20BCBP AST 46.50% fill $929.9M / $2.0BPalantir Maven 81.60% fill $637.6M / $781.3MShield AI USCG $61.4M drawn 12 ordersCounter-drone $2.1B drawn 25 C-UAS vehicles and awardsUSAspending compile · Oct 9 2026
AwardTape

AwardTape · Budget · Reprogramming · FY 26-02

February 2026 monthly action: $54.0M reprogrammed (FY 26-02)

DoD asked the congressional defense committees to approve $54.0M in this prior-approval reprogramming action (FY2026 serial 26-02), dated Mar 6, 2026. Largest increase: System Development & Demonstration +$50.0M (Research, Development, Test and Evaluation, Air Force). Largest source: Combat aircraft -$22.1M (Aircraft Procurement, Air Force).

TypePrior approval (DD 1415-1)
SerialFY 26-02
Document dateMar 6, 2026 from PDF metadata
Transfer between appropriationsYes
Stated total$54.0M increases · $54.0M decreases
Parse checkParsed line items match the totals printed on the form ($54.0M in increases).
SourceDD 1415 PDF · 2 pages, 2 read by OCR
Summary on the form

This reprogramming action transfers $54.0 million between Air Force appropriations. This reprogramming action uses $54.0 million of general transfer authority pursuant to section 1412 of division A of Public Law 119-4, the Full-Year Continuing Appropriations Act, 2025.

Accountsfrom and to
AppropriationYearsChange
Research, Development, Test and Evaluation, Air Force
receives
25/26+$54.0M
Aircraft Procurement, Air Force
gives
25/27-$54.0M
Increases2 lines · +$54.0M
ProgramProgram baseChangeRevised
System Development & Demonstration
Research, Development, Test and Evaluation, Air Force 25/26 · BA 05: System Development & Demonstration
Funds are required to procure one VC-25B full-motion simulator for pilot training and concurrency for Presidential Airlift Group operations at Joint Base Andrews. The delivery lead time for the simulator is 24-28 months, post contract award. The simulator is needed to support the ...
Base $583.9M+$50.0MRevised $633.9M
0205219F MQ-9 UAV
Research, Development, Test and Evaluation, Air Force 25/26 · BA 07: Operational system development
Funds are required for a Joint Urgent Operational Need to integrate and test proliferated low earth orbit capabilities on eight previously procured kits. This capability will improve bandwidth, throughput, air and ground interference mitigation, and flexibility to perform operati ...
Base $7.1M+$4.0MRevised $11.1M
Decreases (sources)3 lines · -$54.0M
ProgramProgram baseChangeRevised
Combat aircraft
Aircraft Procurement, Air Force 25/27 · BA 01: Combat aircraft
Funds are available and early to need for the F-35 Helmet Mounted Display Systems. The initial production contract award was delayed from the fourth quarter of FY 2025 to the second quarter of FY 2026 due to additional time required to finalize contract terms. This requirement wi ...
Base $4.5B-$22.1MRevised $4.5B
Initial Spares/Repair Parts
Aircraft Procurement, Air Force 25/27 · BA 06: Aircraft spares and repair parts
Funds are available and excess to need for F-15 Eagle Passive Active Warning Survivability System initial spares. The program purchased the required number of spares with prior year funding. Prior year funds were available due to favorable negotiations on initial spares contracts ...
Base $982.5M-$20.4MRevised $962.1M
Other Production Charges
Aircraft Procurement, Air Force 25/27 · BA 07: Aircraft support equipment and facilities
Funds are available and early to need due to the T-7A depot facility construction contract award delay from the first quarter of FY 2026 to the second quarter of FY 2027. The delay is primarily driven by a project labor agreements injunction with an expected six-month litigation ...
Base $1.5B-$11.5MRevised $1.5B
Timing

Budget books show money requested, enacted and spent by fiscal year before contracts show it. Enacted procurement money stays available to obligate for 3 years, RDT&E for 2 years and shipbuilding for 5, so a line funded this year turns into contract awards over the following 1 to 5 years. DoD contract actions then publish on USAspending about 90 days after signing (DFARS PGI 204.6), so the awards database trails these budget lines by months to years. Reprogramming actions move enacted money between accounts during the year, usually ahead of the awards it funds.

Terminal: budget lines matched to contracts and companies, with alerts when funding moves.

7 days free for first-time subscribers, then $49/mo. Card required. Cancel before day 8 and you pay nothing.

Start free trial