B-21 Raider: $3.2B FY2027 request
The Air Force requests $3.2B for B-21 Raider in the FY2027 budget (Procurement (P-1) line 1, Aircraft Procurement, Air Force). That is -56% from $7.3B in FY2026 (FY2026 Total). FY2025: $2.6B (FY2025 Total).
| Exhibit | Procurement (P-1) |
|---|---|
| Appropriation | Aircraft Procurement, Air Force 3010F |
| Budget activity | 01 Combat aircraft · Strategic Offensive |
| Line item number | B02100 |
| Service or agency | Air Force (F) |
| Award category | Aircraft in the awards database |
| Budget book | Prior year | Current year | Request | Request quantity |
|---|---|---|---|---|
| FY2027 President's Budget | FY2025 Total $2.6B FY2025 Total | FY2026 Total $7.3B FY2026 Total | $3.2B | |
| FY2026 President's Budget | FY2024 Actuals $2.3B FY2024 Actuals | FY2025 Enacted $2.6B FY2025 Enacted | $5.6B | |
| FY2025 President's Budget | FY2023 Actuals $1.7B FY2023 Actuals | FY2024 PB Request with CR Adjustments $2.3B FY2024 PB Request with CR Adjustments | $2.7B |
| Column | Amount | Quantity |
|---|---|---|
| FY2025 Actuals | $2.6B | |
| FY2025 Total | $2.6B | |
| FY2026 Discretionary Enacted | $2.8B | |
| FY2026 PL 119-21 Spend Plan | $4.5B | |
| FY2026 Total | $7.3B | |
| FY2027 Discretionary Request | $3.2B | |
| FY2027 Total | $3.2B |
| Cost type | Request |
|---|---|
| Weapon System Cost | $3.1B |
| Less: Advance Procurement (PY) | -$862.0M |
| Advance Procurement (CY) | $1.0B |
| C (FY 2025 for FY 2026) (M) memo row, not added | n/a |
| C (FY 2026 for FY 2027) (M) memo row, not added | n/a |
| C (FY 2027 for FY 2028) (M) memo row, not added | $1.0B |
| Award | Company | Obligated FY2024+ |
|---|---|---|
| W9128F24C0013 Department of the Army · names B-21 | CONTI FEDERAL SERVICES, LLC | $140.8M |
| W9128F24C0014 Department of the Army · names B-21 | CONTI FEDERAL SERVICES, LLC | $67.5M |
| W9128F25CA050 Department of the Army · names B-21 | FEDERAL CONTRACTING INC | $59.7M |
| FA466125F0048 Department of the Air Force · names B-21 | CITRINE-OLSSON JV LLC | $1.7M |
| FA462525C0018 Department of the Air Force · names B-21 | ANDURIL INDUSTRIES, INC. | $1.4M |
| FA680026F0007 Department of the Air Force · names B-21 | DEFTEC CORPORATION | $1.3M |
Matched by the program designator in the award description (B-21), same service first plus the largest DoD-wide matches. Budget lines and contracts share no common key, so treat these as leads.
Budget books show money requested, enacted and spent by fiscal year before contracts show it. Enacted procurement money stays available to obligate for 3 years, RDT&E for 2 years and shipbuilding for 5, so a line funded this year turns into contract awards over the following 1 to 5 years. DoD contract actions then publish on USAspending about 90 days after signing (DFARS PGI 204.6), so the awards database trails these budget lines by months to years. Reprogramming actions move enacted money between accounts during the year, usually ahead of the awards it funds.
Source: Office of the Under Secretary of Defense (Comptroller), budget materials: Exhibit P-1 (procurement) and Exhibit R-1 (RDT&E) spreadsheets for the FY2025, FY2026 and FY2027 President's Budget requests. Amounts are in dollars (the exhibits print thousands). Totals add the rows the exhibits count toward totals and leave out memo (non-add) rows. Built Oct 8, 2026. Not investment advice.